1) New Military Hospital Dr. Alejandro Davila Bolaņos School. Installation and construction complete electrical design of buildings 3, 4, 6 and 7; Basement and other plants of the same buildings. Such as Pipes, Rush installation panels Main, Sub panels, Installation of Dry transformers, disconnectors, boxes of records, installation of interior lighting, outlets, Internal Labeling, Etc.

Channeling voice and data network, fire fighting system and PA system.

 

 

 

2) New La Virgen Mall. Construction and Installation complete electrical design Commercial Square including: Installing Red Earth Perimeter of Buildings Thermoweld Welding, Installation of PVC pipe, EMT, IMC from 24 Measurement Modules Commercial Modules, Installation of Exterior Lighting parking areas, Installation of Exterior Lighting LA COLONIA Super Market.

Installation of lighting and currents takes hallways and common Levels 2, Installing Main Panel, Automatic Transfer and Distribution Panels Mall areas.

 

3) VF (Vanity Fair).  Complete electrical design and Installation of factory including: high of voltage distribution lines, installation of (3) 1000 KVA pad mounted transformers, installation of 9 dry transformers 480v/120-208V, electrical installation of  950 KVA and 750 KVA generators, installation of 4800 AMP substations interconnected with 18 cabinets, construction of machine room, installation of 3 air compressors 250HP, 150HP and 100HP, 2 air dryers, installation of 190 power feed rails busway type for three-phase machines of  production lines,  installation of 1,100 luminaires 277v (2 x75W), installations of (3) 1600 AMP main panels and 11 electric sub panels, general polarization equipment, installation of mechanical workshop, electrifical installation on line  9  air-conditioning units.

 

 

4) Conamerica, S.A.  Hampton Hotel. Installation of high voltage distribution lines, 750 KVA pad mounted transformer, installing 500 KW electric generator and transfer switch, construction of machine room, installation of 849 lamps, installation of 711 industrial type  outlets, installation of lightning rods, Installing 2000 amp main panel, instalation of 18 electric sub panels, general polarization equipment, installation of grounding system around the building structure, installation of water pumps for emergency system, installation of elevator system.

 


 

5) GatorNica Complete electrical design and installation of factory including: installation of high voltage distribution lines, 750 KVA pad mounted transformer, installing 350 KW electric generator and transfer switch, installation of 50 HP compressors and air dryer, installing 60 AMP power feed rails busway type for three-phase machines of  production lines, installation of 372 lamps (2 x75W), installation of 1750 amp main panel and 11 electric sub panels, general polarization equipment, installation of mechanical workshop, installation of 24 extractors fans. 

 

 

 

6) Conamerica, S.A. Hospital del Maestro in Diriamba. Installation of high voltage distribution lines,  300 KVA pad mounted transformer, installing 150 KW electric generator and automatic transfer switch, installation of 596 lamps and 165 light switches, installation of 312 special hospital type outlets, electrical installation  of all surgery rooms, installation of telephone system, installation of 800 amp main panel, instalation of 5 electric sub panels, general polarization equipment, installation of grounding system around the building structure, installation of water pumps for emergency system.

 

 

7) Knitwear, S.A. (Index Free Zone) Complete electrical design and installation of factory including: high voltage distribution lines, installing 500 KVA pad mounted transformer, installing 275 KW electric generator, transfer switch,  complete construction of machine room, installation of air compressor and air dryer, installation power feed rails busway type for three-phase machines of  production lines, installation of 350 luminaires (1x75w), installation of 1200 amp main panel and 6 electric sub panels, general polarization of the equipments, general installation of mechanic workshop, installation of 22 extractors fans, installation of rail lines for lighting.

 

 

8) Confecciones de Nicaragua (Industrial Free Zone) Installation of the factory including: high voltage distribution lines,  installing 500 KVA pad mounted transformer, Installing 275 KW electric generator, transfer switch, complete construction of machine room, installation of air compressor and air dryer, installation power feed rails busway type for three-phase machines of  production lines, installation of luminaires to work areas, installation of 1200 amp main panel and Electric Sub Panels, General Polarization of the equipments, General installation of mechanical workshop, installation of extractor fans, installation of rail lines for lighting.

 

 

9) Press 2 Call Center Complete electrical design and installation of factory including: high voltage distribution lines, installing 500 KVA pad mounted transformer, installing 275 KW electric generator, transfer switch,  installation of 350 lamps for  work areas (2x75W), installation of 1200 amp main panel and 6 electric sub panels, electrical installation of computer room, installation of air conditioning unit.

 

 

 

10) Sovipe Ingenieros Energy audits throughout the office complex, resuting in the covery of 12 months of erroneous billing.

 

 

 

 

11) Alfanumeric, S.A. Installing 175KW power generator, transfer switch remodeling circuits of computer operators, outlets, lights and electrical distribution panels.

 

 

 

 

12) Armol Trading Co. Connection of electrical installations, high voltage distribution lines, Main Panel, Design and Installation of internal outlet circuits, lighting, telephone and air conditioning, installation of electrical fuel pumps, Installation of Air compressor and water pressure  machine.

 

 

 

 

13) Caronica, S.A. (Index Free Zone ) Complete electrical design and installation of factory including:  high voltage distribution lines, installing 500 KVA pad mounted transformer, 275 KW electric generator and transfer switch, general construction of machine room, installation of air compressor and air dryer, installation power feed rails busway type for three-phase machines of  production lines, installation of 130 luminaires for the factory with capacity of (1 x 75W), installation of 1200 AMP main panel and 4 electric sub panels 225 AMP  capacity, general polarization of the equipments, installation of mechanic workshop, installation of 10 extractor fans, installation of rail lines for lighting.